Portfolio Fast Track: From Request to Delivery

This guide walks you through the entire portfolio lifecycle — from submitting your first request to delivering a finished project. It's designed to get you productive fast, not to cover every option. For full details, see the Portfolio reference docs.


The Big Picture

Portfolio Workflow Overview

Every initiative in KANAP follows the same flow:

Stage What Happens
Request Someone submits an idea or need
Evaluate A committee scores it for value and feasibility
Approve Decision-makers greenlight (or reject) it
Project The approved request becomes a project with a team, timeline, and effort estimates
Deliver The team executes, logs time, and tracks progress to completion

This pipeline ensures every initiative is evaluated fairly, prioritized transparently, and tracked consistently. No more pet projects jumping the queue.

Why this matters

The scoring and evaluation step is what makes the difference between a wish list and a real portfolio. It gives leadership a defensible, data-driven basis for saying yes — or no.


Step 1: Submit a Request

Go to Portfolio > Requests and click + New Request.

Fill in the minimum fields to get started:

Field What to enter
Name A clear, concise title for the initiative
Purpose What problem does this solve? One or two sentences.
Source Where did this come from? (Business unit, regulation, IT strategy…)
Category The type of initiative (e.g., New Application, Infrastructure, Process Improvement)
Requestor Who is asking for this?
Target Date When is this ideally needed by?

Click Save. Your request is now in the pipeline with status New.

Keep it lean

You can add attachments, detailed descriptions, and links later. The goal right now is to get the request into the system so it can be evaluated.

For all available fields and options, see Requests reference.


Step 2: Evaluate and Score

This is the most important step in the process. It's what turns a backlog of requests into a prioritized, defensible portfolio.

Who Should Score?

Don't score alone

Scoring works best when done by a committee with diverse perspectives. Aim to include representatives from:

  • IT Functional — understands business processes and application landscape
  • IT Technical — understands infrastructure, architecture, and technical debt
  • Cybersecurity — assesses risk, compliance, and security implications
  • Business — validates strategic alignment and business value

A single person's score is an opinion. A committee's score is a decision framework.

Scoring Criteria

Open the request and navigate to the Evaluation section. You'll score the request across multiple criteria on a weighted scale.

The scoring criteria assess the initiative's value and priority:

Criterion What you're assessing
Strategic Alignment How well does this support the organization's strategy?
Business Value What's the expected return — revenue, savings, efficiency?
Urgency Is there a deadline, regulation, or burning platform?
Risk of Inaction What happens if we don't do this?
Dependencies Does this block or enable other initiatives?

Each criterion is scored on a scale, and KANAP calculates a weighted total that lets you compare requests objectively.

Feasibility Analysis (7 Dimensions)

Beyond value, you need to assess whether this is actually doable. The feasibility analysis covers seven dimensions:

Dimension Key question
Technical Feasibility Can we build this with our current tech stack and skills?
Resource Availability Do we have the people?
Budget Can we fund this?
Timeline Is the target date realistic?
Organizational Readiness Is the business ready for this change?
Risk What could go wrong, and can we manage it?
Vendor / External Do we depend on third parties, and are they reliable?

Each dimension gets a rating. Together, they paint a realistic picture of delivery confidence.

The Analysis Recommendation

After scoring and feasibility, write the Analysis Recommendation. This is a short narrative summary — typically 2–4 sentences — that captures the committee's verdict:

Good recommendation examples

  • "High strategic value, strong business case. Technical feasibility is moderate due to legacy integration. Recommend approval with a proof-of-concept phase."
  • "Low urgency, limited business impact. Resource constraints make Q2 delivery unlikely. Recommend deferral to H2."

The combination of scores + feasibility + recommendation gives decision-makers everything they need to approve or reject — without having to sit through a two-hour presentation.

Transparency is the point

When stakeholders ask "why was my request rejected?" or "why did that project get priority?", the evaluation data provides the answer. This is what makes the pipeline fair.

For detailed scoring configuration and weight management, see Settings reference.


Step 3: Approve and Convert

Once the evaluation is complete, it's decision time.

  1. Review the scores, feasibility, and recommendation
  2. Set the status to Approved (or Rejected / Deferred)
  3. Click Convert to Project

Seamless handoff

When you convert a request to a project, all the data carries over automatically — name, description, category, requestor, evaluation scores, and more. No re-entry needed.

The request status changes to Converted, and a new project is created and linked back to the original request.

For requests that aren't approved, you can set them to Rejected with a reason, or Deferred to revisit later.

See Requests reference for all status transitions.


Step 4: Set Up Your Project

Your new project inherits the request data, but it needs a few things before execution can begin.

Go to Portfolio > Projects and open your newly created project.

Team Tab — Assign Your People

Set up the project team with clear roles:

Role Who Purpose
Sponsor Senior business or IT leader Accountable for outcomes, removes blockers
IT Lead Technical project manager Drives IT delivery
Business Lead Business-side project manager Drives business readiness and adoption
Contributors Team members (IT and Business) Do the actual work

Contributors must be configured first

For capacity planning to work, every contributor must be set up in Portfolio > Contributors (also known as Team Members) with:

  • Their team assignment
  • Availability (days per month)
  • Skills

Without this data, the roadmap generator can't calculate capacity, and your planning will be flying blind. See Team Members reference.

Progress Tab — Set Effort Estimates

Enter the estimated effort for the project:

  • IT Effort (MD) — Total man-days expected from IT contributors
  • Business Effort (MD) — Total man-days expected from business contributors

These numbers feed the roadmap

The roadmap generator uses these effort estimates, combined with contributor availability, to automatically schedule projects on the timeline. More accurate estimates = better roadmaps.

Timeline Tab — Apply a Phase Template (Optional)

If your organization has defined phase templates (e.g., "Standard Project", "Agile Sprint Cycle"), you can apply one here to instantly scaffold your project timeline with predefined phases and milestones.

You can also set dates manually or skip this entirely for simpler initiatives.

See Projects reference for all project configuration options.


Step 5: Track Execution

Now the real work begins. As the project progresses, keep KANAP updated.

Update Progress

Use the Execution Progress slider on the Progress tab to reflect how far along the project is. This is a simple percentage (0–100%) that feeds dashboards and reports.

Move the project through statuses as work advances:

In ProgressIn TestingDone

Log Time — This is Critical

No time logging = no automatic scheduling

Time logging isn't just for reporting — it directly powers the roadmap generator.

There are two places to log time:

  1. Progress tab — Log project-level overhead time (meetings, coordination, management)
  2. Tasks — Log task-specific time against individual work items

Here's why this matters:

Time logged → Contributor time statistics → Historical capacity data
                                          → Roadmap generator (historical mode)
                                          → Accurate future scheduling

The roadmap generator has a historical capacity mode that uses actual logged time to understand how much each contributor really delivers per month (as opposed to their theoretical availability). Without time data, the generator falls back to theoretical estimates — which are almost always optimistic.

Make it a habit

Encourage team members to log time weekly. Even rough entries are far better than nothing. The data compounds over time and makes each roadmap iteration more accurate.

Status Transitions

Status Meaning
In Progress Active work is happening
In Testing Deliverables are being validated
On Hold Temporarily paused (capture the reason)
Done All deliverables accepted, project complete
Cancelled Stopped before completion

See Projects reference for details on each status.


Step 6: Structure with Phases and Tasks (Advanced)

For larger projects, you'll want more granular tracking.

Phases

Phases break the project into logical stages (e.g., Analysis, Development, Testing, Deployment).

  • From template: Apply a phase template from the Timeline tab to get a predefined structure
  • Custom: Add phases manually with names, start/end dates, and owners

Each phase can have its own status, progress, and assigned team members.

Tasks

Within each phase (or at the project level), create tasks for specific work items.

  • Assign tasks to contributors
  • Set due dates and priorities
  • Log time directly against tasks
  • Link tasks to phases for structured tracking

Milestones

Mark key checkpoints — go/no-go decisions, deliverable deadlines, or external dependencies.

Milestones appear on the project timeline and in reports, giving stakeholders clear visibility into upcoming decision points.

Start simple, add structure as needed

You don't need phases and tasks for every project. Small initiatives can be tracked with just the progress slider and status. Add structure when the project is complex enough to need it.

For full details on phases, tasks, and milestones, see Projects reference and Planning reference.


How It All Connects

Every piece of data you enter feeds into something bigger. Here's why it's worth the effort:

Automatic Roadmap Scheduling

The roadmap generator takes your project effort estimates, contributor availability, and historical time data to automatically schedule projects across the timeline. No more manual Gantt chart gymnastics.

See Planning reference.

Capacity Heatmaps

Contributor availability and project assignments combine to show you who's overloaded and who has bandwidth — across teams and time periods. This prevents the classic "everyone is assigned to 5 projects at 100%" problem.

Bottleneck Analysis

When multiple projects compete for the same contributors or skills, KANAP highlights the bottleneck so you can make trade-offs before they become crises.

Executive Reporting

Evaluation scores, project status, progress, budget, and timeline data roll up into portfolio-level reports that give leadership a clear picture without manual PowerPoint creation.

See Reporting reference.


Quick Reference

I want to… Go to…
Submit a new idea Portfolio > Requests > + New
Score a request Open request > Evaluation section
See the project pipeline Portfolio > Planning
Check team capacity Portfolio > Planning > Capacity view
Log time on a project Open project > Progress tab or Tasks
Generate a roadmap Portfolio > Planning > Generate
View reports Portfolio > Reporting
Configure scoring weights Portfolio > Settings
Set up contributors Portfolio > Contributors

You're ready

You now know the full lifecycle from request to delivery. Start with a request, score it properly, and let KANAP handle the rest. For detailed documentation on every feature, explore the Portfolio Management section.